At the forward end of the engine room, the shipwrights have been installing heavy timbers which will bear the weight of two 4500 litre diesel fuel tanks. New tanks are being fabricated, as the old tanks were found to be deficient in metal thickness.
A new section of deck beam was required above the bulkhead forward of the main deckhouse. The scarf joints in the old beam are seen here ready to receive the new section.
Eighty plywood sheets for the under layer of deck have been prepared with a V groove similar in appearance to the underside of a traditional laid deck. Sheets are being pre-coated with epoxy paint prior to installation. This pre-coating will minimise overhead painting after the sheets are installed and the use of epoxy paint ensures bonding with the glue applied to the deck beams.